In general, the production manager is responsible for the materials price variance. True or false?.

Respuesta :

PallasAthena23
PallasAthena23 PallasAthena23
  • 01-08-2022
False

In general, materials price variance is the responsibility of the purchasing manager, not the production manager.
Answer Link

Otras preguntas

How does online gaming affect the health of the student
certain substances are placed in the beaker in given picture if the following items are placed in a water filled beaker then state in what condition it remain 1
1-3 Function Operations and Composition Let f(x) = 4x - 7 and g(x) = 5 + 9x. What are f + g and f-g? What are their domains? о А. (f + g)(x) = 13x – 2; (f - 9)(
The history of environmental science progresses the same as the progression of human _____ throughout the ages
The tone of this speech could best be described as expressing a feeling of fear. hope. anger. pride.
What are three different types of hospitals
The American colonies said there should be no taxation without representation. In 1766, Parliament responded by passing the Declaratory Act. Stamp Act. Sugar Ac
what is the solution to the equation 1/x=x+3/2x^2
2x-y-z=15 4x+5y+2z=10 -X-4y+3z=-20​
3х – 8 +7х + 10 А 10x + 2 В 4х – 80 с 21х - 80 D — 5х + 17х