Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Solve this and get 20 points
Put the equation into this form
hey i need help pleaseee
What's the difference between the two types of Mayan pyramids?
Translate the following into french I wake up, shower, brush my teeth, brush my hair, eat breakfast, do homework, read, do chores, do yoga, pet my dog
please help travelling 14m to the right first and travelling 19m to the left . calculate the final position
4 / u^2 (when u = 2)
Tulsa Virtual Academy is hosting a Reading Workshop and Math Workshop for its 240 students. % of students registered for the Math Workshop, % of the remaining s
Which equation is correct? (6 points) cot x° = opposite ÷ adjacent sec x° = opposite ÷ adjacent sec x° = adjacent ÷ opposite cot x° = adjacent ÷ opposite
Find (fxg)(a)?thanks !!